Ansal Properties v. Jain

NCDRC · 2026 NCDRC 427 · Bench: Justice Suresh Kumar, Presiding Member Bharatkumar Pandya

  • Decided: 2026-05-15
  • Subject: Contract Law
  • Provisions: Section 18 RERA 2016; Section 14(1)(d) Consumer Protection Act 2019 (compensation); Section 72 ICA (force majeure)
  • Outcome: Appeal Dismissed
  • Good-law status: Good Law

Facts

Developer delayed possession of a flat by 5 years beyond the agreed date citing regulatory approvals and COVID disruption. Buyer claimed compensation.

Issue

Is a real estate developer liable for delay in possession even where general force majeure conditions exist?

Held

A real estate developer who delays possession beyond the contractually agreed date is liable to pay compensation at the rate prescribed in the Builder-Buyer Agreement and additionally for mental agony. The developer cannot escape liability by citing force majeure conditions that were not disclosed at the time of entering the agreement.

Ratio decidendi

RERA Section 18 creates a strict liability for possession delay. Force majeure must be specifically pleaded with evidence and must relate to the specific project, not market conditions generally. COVID delay confers some relief only for the COVID period.

Exam notes

RERA + Consumer Protection Act for housing complaints. Section 18 RERA = strict liability for delay. NCDRC and RERA have concurrent jurisdiction for compensation.